31.07.2018, 10:36

I. Metshin: “The school in the Solovyinaya Roscha must be completed no later than early September of next year”

The Mayor of Kazan inspected the construction of the school for 1224 places on Gareev Street.

(KZN.RU, July 31, Ksenia Shvetsova). The construction of the school in the RC “Solovyinaya Roscha” on Gareev Street is planned to be completed next year. Ilsur Metshin, the Mayor of Kazan, inspected the progress of work and instructed not to delay with the delivery of the facility. The school should welcome its first students in September 2019.

Azat Nigmatzyanov, the first deputy head of the Executive Committee, said that according to the draft plan for the allocated site, it is planned to build two schools for 1224 places each with a common sports ground. The contractor OOO “Ak Tash” promises to deliver the first school in 2019.

The school is built according to the federal program and will be an ordinary one, as one on the Minskaya Street in the micro-district Azino, which will also open its doors next year. It will be a modern educational institution with two pools (25 and 12 meters), two sports halls, and modern equipment. It will provide all levels of education from 1 to 11 grades.

The Mayor noted that there is a strong need for a new school due to the active development of the micro-district. “We have a very high priority there; a large number of complaints came from the citizens about the need for a new school. This micro-district is being built up very quickly. This imposes responsibility”, said I. Metshin. He also instructed not to delay the construction terms. “It is important to meet all the deadlines and check the quality of work. It is necessary that the school was completed not later than the beginning of September, the beginning of the school year. So that by that time, a director was already appointed, and a collective was formed”.

Several more schools are being built in Kazan. In the 2018-2019 school year, schools will be delivered in the RC “Svetlaya Dolina” and the RC “Salavat Cupere”, and next year, in the RC “Vwsna”.

Andrey Lobov, the head of the Vakhitovsky and Privolzhsky districts’ administration, Ilnar Khidiyatov, the head of the Department of Education, Stanislav Shyrybyrov, the deputy director of the GISU RT, and others took part in the meeting.

Photo report
The Mayor of Kazan inspected the construction of the school on Gareev Street
Video report
31.07.2018 10:30
The Mayor of Kazan inspected the construction of the school on Gareev Street
All news

I. Metshin: “The school in the Solovyinaya Roscha must be completed no later than early September of next year”

<p> (KZN.RU, July 31, Ksenia Shvetsova). The construction of the school in the RC “Solovyinaya Roscha” on Gareev Street is planned to be completed next year. Ilsur Metshin, the Mayor of Kazan, inspected the progress of work and instructed not to delay with the delivery of the facility. The school should welcome its first students in September 2019. </p> <p> </p> <p> Azat Nigmatzyanov, the first deputy head of the Executive Committee, said that according to the draft plan for the allocated site, it is planned to build two schools for 1224 places each with a common sports ground. The contractor OOO “Ak Tash” promises to deliver the first school in 2019. </p> <p> </p> <p> The school is built according to the federal program and will be an ordinary one, as one on the Minskaya Street in the micro-district Azino, which will also open its doors next year. It will be a modern educational institution with two pools (25 and 12 meters), two sports halls, and modern equipment. It will provide all levels of education from 1 to 11 grades. </p> <p> </p> <p> The Mayor noted that there is a strong need for a new school due to the active development of the micro-district. “We have a very high priority there; a large number of complaints came from the citizens about the need for a new school. This micro-district is being built up very quickly. This imposes responsibility”, said I. Metshin. He also instructed not to delay the construction terms. “It is important to meet all the deadlines and check the quality of work. It is necessary that the school was completed not later than the beginning of September, the beginning of the school year. So that by that time, a director was already appointed, and a collective was formed”. </p> <p> </p> <p> Several more schools are being built in Kazan. In the 2018-2019 school year, schools will be delivered in the RC “Svetlaya Dolina” and the RC “Salavat Cupere”, and next year, in the RC “Vwsna”. </p> <p> </p> <p> Andrey Lobov, the head of the Vakhitovsky and Privolzhsky districts’ administration, Ilnar Khidiyatov, the head of the Department of Education, Stanislav Shyrybyrov, the deputy director of the GISU RT, and others took part in the meeting. </p>